nav emailalert searchbtn searchbox tablepage yinyongbenwen piczone journalimg journalInfo journalinfonormal searchdiv searchzone qikanlogo popupnotification paper paperNew
2013, 05, v.32;No.205 8-11
输电线路引流板带电消缺作业安全性校核
基金项目(Foundation): 浙江省电力公司2011年科技项目
邮箱(Email):
DOI: 10.19585/j.zjdl.2013.05.003
摘要:

为确保输电线路引流板带电消缺作业的安全,以220 kV线路SJ41杆塔为例,分析带电作业的安全性。计算得到开展引流板带电消缺作业时,作业人员的作业间隙及作业危险率,为工作人员的作业安全提供有力保证。

Abstract:

In order to ensure the safety of live defects elimination on current plate of transmission lines,the paper takes SJ41 tower of 220 kV lines as an example to analyzes the safety of live work,conclude the work clearance of the operators and hazard index during live defects elimination on current plate,which provides guarantee for work safety of the operators.

参考文献

[1]胡建勋,刘凯,刘庭,等.500 kV高海拔紧凑型输电线路带电作业试验研究[J].高压电器.2010,46(4):35-39.

[2]胡毅,王力农,舒印彪.带电作业保护间隙的放电特性研究[J].高电压技术,2002,28(11):17-18.

[3]郝旭东,朱芸,李雪彦,等.220 kV紧凑型线路带电作业的研究与工具开发[J].电力设备,2007,8(8):17-18.

[4]KIM D S,KOREA ELECTR CONTRACTORS ASSOC,SEOUL,et al.Analysis of electrical safety level test for barehand work at 765 kV vertical double circuit six bundle conductors T/L in Korea[J].IEEE,2009,6(3):1-5.

[5]XU YING,YE ZHENG,GAO XU,et al.The Live Line Inspection Method of Poor Insulators on±500 kV DC Transmission Lines[J].IEEE,2012,9(3):750-753.

[6]IEC 60071-2-1996 Insulation Coordination Part 2 Application Guide[S].1996.

[7]GB/T 16927.1-1997高电压试验技术第一部分:一般试验要求[S].北京:中国电力出版社,1997.

[8]丁一正,谈克雄.带电作业技术基础[M].北京:中国电力出版社,1998.

[9]胡毅.送变电带电作业技术[M].北京:中国电力出版社,2004.

基本信息:

DOI:10.19585/j.zjdl.2013.05.003

中图分类号:TM75

引用信息:

[1]朱丹,梁炜,曾东,等.输电线路引流板带电消缺作业安全性校核[J],2013,32(05):8-11.DOI:10.19585/j.zjdl.2013.05.003.

基金信息:

浙江省电力公司2011年科技项目

检 索 高级检索

引用

GB/T 7714-2015 格式引文
MLA格式引文
APA格式引文