火电机组烟气脱硫改造工程电气设计若干问题的探讨Discussion on Problems of Electrical Design in Flue Gas Desulphurization Transformation of Thermal Power Units
周平,吴顺根
ZHOU Ping,WU Shun-gen(Zheneng Jiaxing Power Generation Co.
摘要(Abstract):
根据实际现场工程情况,对脱硫系统电气接线、容量选择、脱硫保安电源、直流系统以及UPS系统等几个方面进行详细的讨论和分析。从提高运行可靠性角度出发,为电气设计的优化提出建议。
This paper discusses and analyzes desulphurization system electrical wiring,capacity selection,desulphurization emergency power supply,direct current system and UPS system according to the on-site engineering situation.The proposals on optimization of electrical design are put forward to improve the operation reliability.
关键词(KeyWords):
火电机组;烟气脱硫;改造;电气设计;探讨
thermal power units;flue gas desulphurization;transformation;electrical design;discussion