火电厂现场总线设备的调试与问题处理
Commissioning and Problem Handling of Fieldbus Device in Thermal Power Plant

邱深辰,罗志浩,王异成
QIU Shenchen,LUO Zhihao,WANG Yicheng

摘要(Abstract):

介绍了FOUNDATION FIELDBUS现场总线的特点和调试步骤,结合660 MW超超临界燃煤机组的投产调试,从现场总线物理连接层和软件组态配置层2个方面进行了全面的分析,逐一提出了调试运行中应注意的问题,为现场总线的推广应用提供借鉴。
The paper introduces advantages and commissioning steps of FOUNDATION FIELDBUS and comprehensively analyzes physical connection layer and software configuration layer of fieldbus in accordance with the commissioning of 660 MW ultra-supercritical coal-fired units; besides, it presents precautions in commissioning one after another to provide a reference for fieldbus popularization and application.

关键词(KeyWords): 火电厂;FOUNDATION FIELDBUS;现场总线;应用
thermal power plant;FOUNDATION FIELDBUS;field bus;application

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 邱深辰,罗志浩,王异成
QIU Shenchen,LUO Zhihao,WANG Yicheng

DOI: 10.19585/j.zjdl.2016.06.013