浙江电力

2011, v.30;No.187(11) 21-23

[打印本页] [关闭]
本期目录(Current Issue) | 过刊浏览(Archive) | 高级检索(Advanced Search)

改进110kV内桥接线一、二次设备配置的探讨
Discussion on Configuration Improvement for Primary and Secondary Equipments of 110 kV Internal Bridge Connection

周亚,文凡
ZHOU Ya,WEN Fan(Lin′an Power Supply Bureau

摘要(Abstract):

对110 kV内桥接线在实际运行操作中存在的问题进行分析,给出内桥接线一、二次设备配置的改进方案,使得内桥接线方案得到优化,进一步提高内桥接线在电网运行中安全可靠性。
Through the analysis of the problems in the operation of 110 kV internal bridge connection,a scheme of configuration improvement for primary and secondary equipments of the internal bridge connection is put forward so as to optimize the connection scheme and further enhance its safety and reliability in the operation of power grids.

关键词(KeyWords): 改进;内桥接线;设备配置
improvement;internal bridge connection;equipment configuration

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 周亚,文凡
ZHOU Ya,WEN Fan(Lin′an Power Supply Bureau

DOI: 10.19585/j.zjdl.2011.11.007