新能源孤岛柔直送出系统耗能电阻优化配置研究Study on optimal configuration of energy-dissipating resistors in VSC-HVDC system for new energy island
冯燕波,王姗姗,吴广禄,赵兵,尹睿,任永浩,彭红英
FENG Yanbo,WANG Shanshan,WU Ganglu,ZHAO Bing,YIN Rui,REN Yonghao,PENG Hongying
摘要(Abstract):
在新能源孤岛经柔直送出系统中,通过投入等容量分组交流耗能电阻可实现故障穿越期间系统盈余功率的消纳。当单组耗能电阻功率过大时,会对系统造成严重冲击。因此,提出了一种基于进制转换的非等容量交流耗能电阻优化配置方法及其投切策略。首先,分析了等容量分组交流耗能电阻的动作特性。然后,为柔直系统配置单组容量各不相同但总容量与柔直系统容量相等的多组交流耗能电阻,并对不同容量的耗能电阻进行组合,以获得不同的耗能功率。最后,在PSCAD/EMTDC仿真平台上搭建并网模型进行验证。仿真结果表明,采用该方法及投切策略提高了耗能电阻的投切精度,降低了对系统的冲击,缩短了故障恢复时间,实现了对故障穿越期间盈余功率的精准消纳。
In VSC-HVDC system for new energy island, surplus power consumption in the system during fault ridethrough(FRT) is achieved by employing grouped AC energy-dissipating resistors of equal capacity. However, the presence of an excessively powered resistor group can inflict severe impacts on the system. Therefore, a novel optimal configuration method for energy-dissipating resistors with different capacities based on progression conversion and the switching strategy are proposed. Firstly, the operational characteristics of the grouped AC energy-dissipating resistors of equal capacity are analyzed. Subsequently, multiple groups of AC energy-dissipating resistors with varying capacities, collectively equivalent to the total capacity of the VSC-HVDC system, are configured, and different combinations of the resistors are employed to obtain varying dissipating powers. Finally, a model of the integrated grid is constructed and validated using the PSCAD/EMTDC simulation platform. Simulation results demonstrate that the proposed method and switching strategy enhance the precision of resistor switching, mitigate system impacts, shorten fault recovery time, and precisely consumes surplus power during fault ride-through.
关键词(KeyWords):
柔直;故障穿越;盈余功率;耗能装置;二进制
VSC-HVDC;FRT;surplus power;energy dissipation device;binary
基金项目(Foundation): 国家自然科学基金联合基金项目(XT71-21-001)
作者(Author):
冯燕波,王姗姗,吴广禄,赵兵,尹睿,任永浩,彭红英
FENG Yanbo,WANG Shanshan,WU Ganglu,ZHAO Bing,YIN Rui,REN Yonghao,PENG Hongying
DOI: 10.19585/j.zjdl.202407011
参考文献(References):
- [1]《中国能源》编辑部.先立后破有序推进能源结构调整优化[J].中国能源,2021,43(12):1-2.Establishing first,then breaking in order,promoting the adjustment and optimization of energy structure[J]. Energy of China,2021,43(12):1-2.
- [2]饶宏,周月宾,李巍巍,等.柔性直流输电技术的工程应用和发展展望[J].电力系统自动化,2023,47(1):1-11.RAO Hong,ZHOU Yuebin,LI Weiwei,et al.Engineering application and development prospect of VSC-HVDC transmission technology[J].Automation of Electric Power Systems,2023,47(1):1-11.
- [3]鞠平,姜婷玉,黄桦.浅论新型电力系统的“三自”性质[J].中国电机工程学报,2023,43(7):2598-2607.JU Ping,JIANG Tingyu,HUANG Hua. Brief discussion on the“three-self”nature of the new power system[J].Proceedings of the CSEE,2023,43(7):2598-2607.
- [4]饶宏,黄伟煌,郭知非,等.柔性直流输电技术在大电网中的应用与实践[J].高电压技术,2022,48(9):3347-3355.RAO Hong,HUANG Weihuang,GUO Zhifei,et al.Practical experience of VSC-HVDC transmission in large grid[J].High Voltage Engineering,2022,48(9):3347-3355.
- [5]康重庆,陈启鑫,苏剑,等.新型电力系统规模化灵活资源虚拟电厂科学问题与研究框架[J].电力系统自动化,2022,46(18):3-14.KANG Chonging,CHEN Qixin,SU Jian,et al.Scientific problems and research framework of virtual power plant with enormous flexible distributed energy resources in new power system[J].Automation of Electric Power Systems,2022,46(18):3-14.
- [6]吴广禄,周孝信,王姗姗,等.柔性直流输电接入弱交流电网时锁相环和电流内环交互作用机理解析研究[J].中国电机工程学报,2018,38(9):2622-2633.WU Guanglu,ZHOU Xiaoxin,WANG Shanshan,et al.Analytical research on the mechanism ofthe interaction between PLL and inner current loop when VSC-HVDC connected to weak grid[J].Proceedings of the CSEE,2018,38(9):2622-2633.
- [7]赵媛,张静岚,吴文杰,等.柔性直流电网基于交流母线分列运行策略的功率盈余控制方法[J].南方电网技术,2021,15(4):19-25.ZHAO Yuan,ZHANG Jinglan,WU Wenjie,et al.Power surplus control method based on AC bus parallel operation strategy in VSC-based DC grid[J].Southern Power System Technology,2021,15(4):19-25.
- [8]张文建,褚景春,袁凌,等.南非风电场有功储备模式下的功率滚动平滑控制[J].太阳能学报,2019,40(3):635-640.ZHANG Wenjian,CHU Jingchun,YUAN Ling,et al.Rolling smoothing control with active power reservation for wind farms inSouth Africa n[J].Acta Energiae Solaris Sinica,2019,40(3):635-640.
- [9]林俐,朱晨宸,郑太一,等.风电集群有功功率控制及其策略[J].电力系统自动化,2014,38(14):9-16.LIN Li,ZHU Chenchen,ZHENG Taiyi,et al. Active power control of wind farm cluster and its strategy[J].Automation of Electric Power Systems,2014,38(14):9-16.
- [10]韩佶,苗世洪,Martinez-Rico Jon,等.基于机群划分与深度强化学习的风电场低电压穿越有功/无功功率联合控制策略[J].中国电机工程学报,2023,43(11):4228-4244.HAN Ji,MIAO Shihong,Martinez-Rico Jon,et al.Combined re/active power control for wind farm under low voltage ride through based on wind turbines grouping and deep reinforcement learning[J].Proceedings of the CSEE,2023,43(11):4228-4244.
- [11]杨佳涛,吴西奇,李睿,等.中压直挂光伏发电系统模块间电压-功率自主跟踪控制方法研究[J].中国电机工程学报,2021,41(8):2815-2825.YANG Jiatao,WU Xiqi,LI Rui,et al. Research on submodules voltage-power self-tracking control method for medium-voltage direct-linked photovoltaic power generation system[J].Proceedings of the CSEE,2021,41(8):2815-2825.
- [12]路朋,叶林,裴铭,等.风电集群有功功率模型预测协调控制策略[J].中国电机工程学报,2021,41(17):5887-5900.LU Peng,YE Lin,PEI Ming,et al. Coordinated control strategy for active power of wind power cluster based on model predictive control[J]. Proceedings of the CSEE,2021,41(17):5887-5900.
- [13]严伟,王淑超,刘翔,等.光伏系统快速功率控制和应用(英文)[J].中国电机工程学报,2019,39(增刊1):213-224.YAN Wei,WANG Shuchao,LIU Xiang,et al. System level PV fast power control technology and application[J].Proceedings of the CSEE,2019,39(S1):213-224.
- [14]叶林,任成,李智,等.风电场有功功率多目标分层递阶预测控制策略[J].中国电机工程学报,2016,36(23):6327-6336.YE Lin,REN Cheng,LI Zhi,et al.Stratified progressive predictive control strategy for multi-objective dispatching active power in wind farm[J].Proceedings of the CSEE,2016,36(23):6327-6336.
- [15]李书亚,解绍锋,马智泉.孤岛运行方式下柔性直流配网高次谐波谐振及抑制措施研究[J].电力电容器与无功补偿,2023,44(5):81-88.LI Shuya,XIE Shaofeng,MA Zhiquan.Research on high order harmonic resonance and suppression measures of flexible DC distribution network under isolated operation mode[J].Power Capacitor&Reactive Power Compensation,2023,44(5):81-88.
- [16]王楚扬,张秋玥,张犁.计及主站容量裕度的柔性直流互联系统主从控制策略[J].电力工程技术,2023,42(3):81-91.WANG Chuyang,ZHANG Qiuyue,ZHANG Li.Masterslave control strategy of flexible DC interconnection system considering capacity margin of master station[J].Electric Power Engineering Technology,2023,42(3):81-91.
- [17]张晓英,段赛赛,吴丽珍.基于跟踪偏差角和改进迭代误差修正的光伏功率预测优化策略[J].智慧电力,2023,51(4):84-91.ZHANG Xiaoying,DUAN Saisai,WU Lizhen.Optimization strategy of photovoltaic power prediction based on tracking deviation angle&improved iterative error correction[J].Smart Power,2023,51(4):84-91.
- [18]詹红霞,肖竣文,邓小勇,等.计及柔性负荷的高比例风光渗透下配电网孤岛划分策略[J].电力工程技术,2022,41(4):108-116.ZHAN Hongxia,XIAO Junwen,DENG Xiaoyong,et al.Islanding strategy for distribution network with high proportion of wind/photovoltaic penetration considering flexible load[J]. Electric Power Engineering Technology,2022,41(4):108-116.
- [19]朱家宁,张诗钽,葛维春,等.海上风电外送及电能输送技术综述[J].发电技术,2022,43(2):236-248.ZHU Jianing,ZHANG Shitan,GE Weichun,et al.Overview of offshore wind power transmission and power transportation technology[J]. Power Generation Technology,2022,43(2):236-248.
- [20]邓超平,晁武杰,戴立宇,等.基于MMC-BESS和MMCMVDC的柔性直流互联系统运行控制[J].供用电,2023,40(7):41-47.DENG Chaoping,CHAO Wujie,DAI Liyu,et al.Operation control of flexible DC interconnection system based on MMC-BESS and MMC-MVDC[J]. Distribution&Utilization,2023,40(7):41-47.
- [21]邹凯凯,李钢,张宝顺,等.海风柔直陆上主网交流故障穿越协调策略[J].供用电,2022,39(11):18-25.ZOU Kaikai,LI Gang,ZHANG Baoshun,et al.A coordination strategy of offshore MMC during onshore grid AC faults[J].Distribution&Utilization,2022,39(11):18-25.
- [22]随顺科,任铁强,邹强,等.连接风电系统的柔性直流电网MMC在线投入分析与验证[J].供用电,2022,39(11):26-31.SUI Shunke,REN Tieqiang,ZOU Qiang,et al.Analysis and verification of MMC online entry into a flexible DC gridconnected to wind power system[J]. Distribution&Utilization,2022,39(11):26-31.
- [23] CHEN X,LI L. Study of DC chopper circuit based on MATLAB software[C]//2022 2nd International Conference on Electronic Information Engineering and Computer Technology(EIECT),Yan’an,China. IEEE,2022:83-86.
- [24] JIANG Y L,GAO Y Y,QIN X H,et al.The post-fault DC chopper activation in VSC-HVDC systems for offshore wind transmission[C]//2023 6th International Conference on Energy,Electrical and Power Engineering(CEEPE),Guangzhou,China.IEEE,2023:294-298.
- [25]秦善萌,王姗姗,赵兵,等.新能源经柔直孤岛送出场景下换流站安全稳定运行区域研究[J].电网技术,2021,45(2):785-793.QIN Shanmeng,WANG Shanshan,ZHAO Bing,et al.Study on the safe and stable operation area for the converter station under the scenarios of renewable energy generation sending through islanded MMC-HVDC[J].Power System Technology,2021,45(2):785-793.
- [26]张静,高冲,许彬,等.海上风电直流并网工程用新型柔性直流耗能装置电气设计研究[J].中国电机工程学报,2021,41(12):4081-4090.ZHANG Jing,GAO Chong,XU Bin,et al. Research on electrical design of novel flexible DC energy consuming device for offshore wind power DC grid connection project[J].Proceedings of the CSEE,2021,41(12):4081-4090.
- [27]张福轩,郭贤珊,汪楠楠,等.接入新能源孤岛系统的双极柔性直流系统盈余功率耗散策略[J].电力系统自动化,2020,44(5):154-160.ZHANG Fuxuan,GUO Xianshan,WANG Nannan,et al.Surplus power dissipation strategy for bipolar VSCHVDC system with integration of islanded renewable energy generation system[J].Automation of Electric Power Systems,2020,44(5):154-160.
- [28]杨悦民,许超群,刘宇畅,等.基于IGCT复合模块直串接集中电阻的400 kV直流耗能装置原理与研制[J].高电压技术,2022,48(4):1510-1517.YANG Yuemin,XU Chaoqun,LIU Yuchang,et al.Principle and development of 400 kV DC energy dissipation device based on IGCT composite module directly connected to concentrated resistance[J].High Voltage Engineering,2022,48(4):1510-1517.
- [29]许彬,高冲,张静.应用于海上风电接入的VSC-HVDC系统主网侧交流故障穿越的新型直流耗能装置拓扑[J].中国电机工程学报,2021,41(1):88-97.XU Bin,GAO Chong,ZHANG Jing.A novel DC chopper topology for grid side fault ride through in VSC-HVDC based offshore wind power connection[J].Proceedings of the CSEE,2021,41(1):88-97.
- [30]张浩博,向往,文劲宇.应对受端交流故障的海上风电柔直并网系统主动能量控制方法[J].中国电机工程学报,2023,43(12):4600-4614.ZHANG Haobo,XIANG Wang,WEN Jinyu. Active energy control of offshore wind power MMC-HVDC System to handle AC faults of receiving-end power grid[J].Proceedings of the CSEE,2023,43(12):4600-4614.