变电站自动化设备对点调试方法探讨
Discussion about Databank Verification for Substation Automation Equipment

严浩军
YAN Hao-jun(Ningbo Electric Power Bureau

摘要(Abstract):

运行变电站自动化设备的对点调试,往往要涉及设备停电,为此,分析了运行变电站自动化设备对点调试的几种方法及其存在的问题。认为要解决这些问题,变电站自动化设备应增加在线仿真模拟调试功能,或配备仿真模拟调试装置。提出了在线仿真模拟调试功能及仿真模拟调试装置功能需求。
Databank verification for substation automation equipment has been a trouble for power suppliers due to power outage difficulties.This article analyses methods and problems about databank verification in power suppliers.In order to solve these problems,the paper suggests that performance of online simulation debugging test or simulation device should be added.This paper also gives a tentative plan for specific requirements of online simulation testing functions or simulation devices.

关键词(KeyWords): 变电站;自动化设备;对点调试;仿真模拟
substation;automation equipment;debugging of databank corresponding;reality simulation

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 严浩军
YAN Hao-jun(Ningbo Electric Power Bureau

DOI: 10.19585/j.zjdl.2009.04.009

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享