10kV变/配电所消弧保护方式的改进Improvement of Protection Mode of Arc Suppression in 10 kV Substation
王永香
WANG Yongxiang
摘要(Abstract):
雷电或弧光接地过电压往往造成高压配电柜内元器件损坏、甚至爆炸,是变/配电所设备损坏的主要原因,一旦故障发生,会造成大面积和长时间停电。通过故障消弧柜的故障原因查找和消弧保护原理分析,对现有消弧保护方式和避雷措施进行改进。在变/配电所进线电缆处安装零序电流互感器,发生单相弧光接地时,根据零序电流方向判断弧光接地发生在所外还是所内,对所内弧光接地过电压采取消弧控制,所外弧光接地过电压时仅报警,从而减少不必要的消弧控制和因消弧控制而导致系统金属性接地的次数。
Lightning or arc grounding overvoltage often cause damage on components in high voltage power distribution cabinet or even explosion, which is the main cause of equipment damage in substation. Once the failure occurs, it will result in widespread and long-time blackout. Current protection modes of arc suppression and lightning protection measures are improved by searching for failure reason of arc suppression cabinet and analyzing the principle of arc suppression. After installing zero-sequence current transformer on substation incoming cable, it can be determined whether arc grounding happens inside or outside the substation depending on the direction of zero-sequence current in case of single-phase arc grounding. For arc grounding overvoltage inside the substation, arc suppression controls are adopted; for that outside the substation, alarming measures are employed. Thus, the unnecessary arc suppression control as well as the metal grounding times of system caused by arc suppression control can be reduced.
关键词(KeyWords):
雷电波;单相弧光接地;弧光过电压;消弧控制;零序电流
lightning wave;single-phase arc grounding;arc-overvoltage;arc suppression control;zero-sequence current signal
基金项目(Foundation):
作者(Author):
王永香
WANG Yongxiang
DOI: 10.19585/j.zjdl.2014.08.017
参考文献(References):
- [1]王接旭,侯建军,丁晓峰.弧光接地过电压引起设备烧毁事故原因分析[J].电气技术,2011(1):79-81.
- [2]曾海涛,王勇,黄少先.高要10kV高岗线防雷保护的研究[J].电气应用,2009(21):50-53.
- [3]王希,王顺超,何金良,等.10 kV配电线路的雷电感应过电压特性[J].高电压技术,2011(3):599-605.
- [4]王恒山.中性点经消弧线圈接地变为低阻接地故障分析[J].电气应用,2008(17):53-55.
- [5]毛卫华.弧光接地过电压的危害及消弧措施[J].电气应用,2008(10):49-51.
- [6]邬自健,陈式献,杨华,等.XHG消弧装置机理及保护分析[J].冶金动力,2011(S1):4-6.
- [7]周理,沈倪勇.高压电缆绝缘电阻的测试与探讨[J].铁合金,2006(5):27-30.
- [8]江日洪,罗晓宇,曹世勋,等.长电缆线路雷电冲击过电压计算及绝缘配合[J].供用电,2002(2):12-16.
- [9]王希,王顺超,何金良,等.安装避雷器后10 kV配电线路的雷电感应过电压特性[J].电网技术,2012(7):149-154.
- [10]陈辉.采用零序电流互感器检测10 kV线路接地故障的探讨[J].浙江电力,2001(4):52-53.
- 雷电波
- 单相弧光接地
- 弧光过电压
- 消弧控制
- 零序电流
lightning wave - single-phase arc grounding
- arc-overvoltage
- arc suppression control
- zero-sequence current signal