1000MW超超临界机组的化学调试
Chemistry Debugging in 1 000 MW Ultra-supercritical Unit

于志勇,陆继民,王光辉
YU Zhi-yong~1,LU Ji-min~2,WANG Guang-hui~1 (1.Zhejiang Electric Power Test and Research Institute

摘要(Abstract):

介绍了华能玉环电厂1号机组化学调试的内容和特点,总结了经验教训。对调试过程中出现的化学清洗跳泵、EDTA药品配置、受热面加热不匀、辅助管道清洗范围及整套启动水汽品质监督中水质控制等问题和需要注意的事项进行了详细的叙述和分析。
The content and characteristic of chemistry debugging in Unit 1 of Huaneng Yuhuan Power Plant is introduced in this paper.Some problems and transactions which need be noticed are described and analyzed in detail, such as the maintenance of sea water desalting system,trip-pump of chemical cleaning,the collocation of EDTA,non-uniform heating of heating surface,the cleaning range of subsidiary conduit and the water quality control in steam-water quality supervision of complete started stage.Some experiences of chemistry debugging in Unit 1 are summarized,in order to be used for reference in ultra-supercritical unit for the future.

关键词(KeyWords): 超超临界机组;化学;调试
ultra-supercritical unit;chemistry;debugging

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 于志勇,陆继民,王光辉
YU Zhi-yong~1,LU Ji-min~2,WANG Guang-hui~1 (1.Zhejiang Electric Power Test and Research Institute

DOI: 10.19585/j.zjdl.2009.s1.029

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享