1000MW超超临界塔式锅炉燃烧优化调整
Combustion Optimization for 1 000 MW Ultra-supercritical Tower Boiler

潘国清,徐小琼,应明良,蔡洁聪
PAN Guo-qing,XU Xiao-qiong,YING Ming-liang,CAI Jie-cong(Zhejiang Electric Power Test and Research Institute

摘要(Abstract):

通过燃烧优化调整试验,有效地解决了1 000 MW超超临界塔式锅炉长期以来的结焦问题,同时也大大提高了再热汽温,降低了送、引风机的耗电量,增加了送、引风机的裕量,减少了NOX排放浓度,提高了锅炉整体安全性和经济性。
The coking problem of 1 000 MW ultra-supercritical tower boilers which exists for a long time is solved effectively by combustion optimization tests.Meanwhile,the reheating steam temperature is significantly increased.The power consumption of forced and induced draft fans and the NOX emission concentration are reduced and the margins of these draft fans are greatly increased.Therefore the overall safety and economy of boilers are improved.

关键词(KeyWords): 1000MW;超超临界;塔式锅炉;燃烧;优化;调整
1 000 MW;ultra-supercritical;tower boiler;combustion;optimization;adjustment

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 潘国清,徐小琼,应明良,蔡洁聪
PAN Guo-qing,XU Xiao-qiong,YING Ming-liang,CAI Jie-cong(Zhejiang Electric Power Test and Research Institute

DOI: 10.19585/j.zjdl.2011.07.009

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享