嘉兴220kV电网中期运行分区方式研究
Research on Medium-term Partitioning Operation Mode of Jiaxing 220 kV Power Grid

杨晓雷,叶琳,张静炜
YANG Xiao-lei 1,YE Lin 2,ZHANG Jing-wei 1(1.Jiaxing Electric Power Bureau

摘要(Abstract):

针对嘉兴220 kV电网分区现状及存在问题,结合嘉兴电网发展规划,对嘉兴220 kV电网中期运行的分区方式进行研究分析,提出了分阶段逐步完善的分区运行方式,以适应实际电网安全可靠运行的需要。
Aiming at current status of Jiaxing 220 kV power grid partitioning and the existing problems,the paper,by combining development planning of Jiaxing power grid,investigates and analyzes medium-term partitioning operation mode of Jiaxing 220 kV power grid,and proposes to perfect the partitioning operation mode phase by phase to adapt the actual demand of operation safety and reliability.

关键词(KeyWords): 500kV;220kV;分区方式;短路电流
500 kV;220 kV;partitioning mode;short circuit current

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 杨晓雷,叶琳,张静炜
YANG Xiao-lei 1,YE Lin 2,ZHANG Jing-wei 1(1.Jiaxing Electric Power Bureau

DOI: 10.19585/j.zjdl.2013.08.003

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享