智能变电站新增间隔IED装置的接口试验
Research on Interface Testing of Newly-added Bay Level LED in Smart Substation

冯正伟,刘力华,卢洪峰
FENG Zhengwei,LIU Lihua,LU Hongfeng

摘要(Abstract):

以浙江电网500 kV兰溪变电站新建220 kV间隔的IED装置接口试验为例,提出了智能变电站新增间隔的保护装置、智能终端、测控装置等IED装置的接口试验和逻辑验证方案,工程实践证明,该试验方案能有效地验证各IED装置的逻辑关系,同时能大大降低试验的安全风险。
By taking interface testing of newly-built 220 kV bay level IED in 500 kV Lanxi substation of State Grid Zhejiang Electric Power Company as an example, the paper proposes a scheme for interface testing and logic testing of newly-added bay level IED, such as protection device, intelligent terminal as well as measurement and control device. The engineering practice shows that the scheme can effectively verify logic relations among IED and significantly reduce safety risks of the testing.

关键词(KeyWords): 智能变电站;IED装置;GOOSE;状态检修
smart substation;IED;GOOSE;state-based maintenance

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 冯正伟,刘力华,卢洪峰
FENG Zhengwei,LIU Lihua,LU Hongfeng

DOI: 10.19585/j.zjdl.2014.03.006

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享