火力发电机组不投运循环水的分系统调试技术研究Research on Commissioning of Out-of-service Circulating Water Subsystem for Thermal Power Units
陆莹,王达峰,罗辇,胡洲,徐熙瑾
LU Ying,WANG Da feng,LUO Nian,HU Zhou,XU Xi jin
摘要(Abstract):
在火力发电机组基建调试中,循环水系统的施工时间通常受气候、环境的制约,施工期长。为了不影响机组的调试进程,提出了一种在循环水系统不投运的情况下依然能开展其他系统调试的技术。应用于1 000 MW超超临界燃煤机组的调试表明,使用这一技术可大大加快工程的调试进度,具有显著的经济和社会效益。
In capital construction commissioning of thermal power generating units,the construction time of circulating water system is often restricted by climate and environment,and the construction period is often quite long.In order not to affect the process of unit commissioning,the paper proposes a commissioning technique for other systems under circumstance of non-operation of circulating water system.The commissioning of 1 000 MW ultra supercritical coal-fired units shows that the technique can speed up the commissioning and achieve significant social and economical benefits.
关键词(KeyWords):
1 000 MW;火电机组;基建调试;循环水
1 000 MW;thermal power units;capital construction commissioning;circulating water
基金项目(Foundation):
作者(Author):
陆莹,王达峰,罗辇,胡洲,徐熙瑾
LU Ying,WANG Da feng,LUO Nian,HU Zhou,XU Xi jin
DOI: 10.19585/j.zjdl.2013.09.010