变电站鸟害防治措施Preventive Measures against Bird Injury on the Substation
朱晶亮
ZHU Jing-liang(Jiaxing Electric Power Bureau
摘要(Abstract):
为解决长期困扰变电站的鸟害问题,结合输电线路防治鸟害经验,从技术措施、管理措施两方面入手,驱、防、引三者结合综合治理变电站鸟害。
In order to cope with long bedeviled bird injury on substation,the paper,on the basis of technical measures and control measures,proposes a "dispelling,prevention and alluring" integrated bird injury control measure in combination with experience in preventing bird injury on transmission lines.
关键词(KeyWords):
变电站;鸟害防治;技术措施;管理措施
substation;bird injury prevention;technical measures;management measures
基金项目(Foundation):
作者(Author):
朱晶亮
ZHU Jing-liang(Jiaxing Electric Power Bureau
DOI: 10.19585/j.zjdl.2013.02.020